Alfred McAlpine Capital Project Ltd v Tilebox Ltd (2006)

Citation: EWHC 281 (TCC); [2005] B.L.R. 271; 104 Con. L.R. 39

Nature of case:
Already reported in BLR, this case contains a useful review of the modern law on the distinction between liquidated damages and penalties. On the facts, the liquidated damages provision in the JCT WCD 1998 contract for £45,000 per week was a genuine pre-estimate of loss and the actual loss suffered by the developer, Tilebox, was higher.  The contractor therefore failed to obtain a declaration that the provision was a penalty.

See other reports:

BLR 271 TCC

Counsel

  • Share