Alfred McAlpine Capital Projects Ltd v Tilebox Ltd (2005)

Citation: BLR 271 TCC

Nature of case:
This case contains a useful review of the modern law on the distinction between liquidated damages and penalties.  On the facts, the liquidated damages provision in the JCT WCD 1998 for £45,000 per week was a genuine pre-estimate of loss and the actual loss suffered by the developer, Tilebox, was higher.  The contractor therefore failed to obtain a declaration that the provision was a penalty.