Henry Boot Construction Ltd v Alstom Combined Cycles Ltd

Citation: EWCA Civ. 814 LAWTEL CA

Nature of case:
On when the contractor’s right to payment arises and whether (in a ICE 6th contract) the issue of a certificate is a condition precedent to payment.  The right to claim interest on a sum which should have been certified becomes statute-barred six yeas after accrual of the right.

See other reports:

[2005] 101 Con LR 52 CA
[2005] BLR 437 CA
[2005] CILL 2276 and BLM Vol 22 No 9 p.1 CA