William Verry Ltd v NW London Communal Mikvah

Citation: BLR 308 and [2004] 96 Con LR 96

Nature of case:
This concerns time-limits.  Referral to the adjudicator within seven days means from the date the notice was issued, not from the date of service.  However, the referring party could by contract be allowed to take longer.  The adjudicator was held to have erred in deciding that he was precluded from re-valuation of the work.