Earl’s Terrace Properties Ltd v Nilsson Design Ltd

Citation: 94 Con LR 118, [2004] BLR 273, [2007] Lloyd's Rep PN 28 and [2004] EWHC 136 (TCC)

Nature of case:
Already reported in CILL, this is a consideration of the extent and quantum of damages recoverable as commercial loss from delay in refurbishment of dwelling houses and whether a rise in sale prices was to be taken into account in the calculations.

Link to Judgment 

Counsel

Alexander Nissen KC