Henry Boot Construction ltd v Alstom Combined Cycles Ltd (Formerly GEC Alstom Combined Cycles Ltd)

Citation: BLR 247

Nature of case:
Whether the fact that the rates or prices contained in a Bill of Quantities under an ICE Standard Conditions of Contract agreement may have been calculated in error was a ground for departing from those rates or prices as the basis for the valuation of increases in the work.

Counsel

Stephen Furst KC

  • Share