Redworth Construction Ltd v Brookdale Healthcare Ltd

Citation: All ER (D) 04 TCC; CILL 2373; BLM Vol. 23 No.9 p.3; EWHC 1994

Nature of case:
The claimant sought enforcement of an adjudication award in its favour, having made submissions to the adjudicator that its agreement with the defendant was a construction contract on the basis of certain documents.  In the enforcement proceedings, the claimant sought to rely on different documents to support its case, but the court held that the claimant could not change its position.  The evidence did not establish that there was a contract in writing and the enforcement action was dismissed.