Shawton Engineering Ltd v DGP International

Citation: CILL 2306 CA

Nature of case:
This case arose from a design sub-sub-contract relating to a process plant in Sellafield for handling nuclear waste. The issue arose as to the circumstances in which a contracting party could lawfully terminate a contract for delay in performance where the obligation was to complete within a reasonable time.

Link to Judgment