Shawton Engineering Ltd v DGP International Ltd

18 November 2005

Citation: All ER(D) 241 CA

Nature of case: In a design sub-sub-contract relating to a process plant at Sellafield for handling nuclear waste, the issue arose as to the circumstances in which a contracting party could lawfully terminate a contract for delay in performance where the obligation was to complete within a reasonable time. 

Link to full judgement.

See other reports: [2006] CILL 2306 CA [2006] BLR 1 CA [2006] Con LJ Vol.22 No.2 p.129 CA