0

Download your shortlist

Download All

Shepherd Construction Ltd v Mecright Ltd

27 July 2000

Citation: BLR 489; [2000] Lawtel 3/10/2000

Nature of case: A settlement agreement was binding upon the parties in relation to all disputes to which it related until such time as a tribunal of competent jurisdiction determined otherwise.  

Until then, any dispute concerning the subject of that agreement could not be referred to adjudication.