Shawton Engineering Ltd v DGP International Ltd
Citation: BLR 1 CA
Nature of case:
This case arose from a design sub-sub-contract relating to a process plant at Sellafield for handling nuclear waste. The issue arose as to the circumstances in which a contracting party could lawfully terminate a contract for delay in performance where the obligation was to complete within a reasonable time. The appellant sub-contractor was unsuccessful in the appeal.