Lewisham London Borough Council v MR Ltd

Citation: All ER (D) 548 TCC

Nature of case:
The defendant’s supervisory duties did not continue through to practical completion and there was thus no duty to see that poor workmanship was remedied.  The limitation period started to run when the sub-contractor’s work was completed defectively, not at practical completion, so the claims were out of time.

Counsel

  • Share